Requests for sewer design-related revisions to existing permits prior to completion of sewer work under the permit, or to make minor changes to stormwater detention facilities, must include:
|
A letter from the design engineer of the permit describing the
design changes and the reason for the changes, submitted to Justine
Skawski, Principal Civil Engineer of the Local Sewer Systems
Section. |
|
A letter from the municipal/system engineer of the permit
granting approval of the changes. |
|
Four (4) copies of revised design drawings, with each sheet
signed and sealed by the permit design engineer of record (only
those plan sheets that are changed). |
|
Four (4) copies of all revised permit documents signed and sealed
by the permit design engineer of record (if applicable). |
|
Permit revision fee payment $500.00 plus $5.00 per linear foot of
additional sewer length. Fees are waived for governmental sewer
projects (public sewer mains, laterals for
fire/police stations, libraries, etc.). |
Justine Skawski
Engineering Department - Local Sewer Systems Section
Metropolitan Water Reclamation District of Greater Chicago
111 East Erie Street
Chicago, IL 60611-2893
|